The workfront

What the project required.

The challenge

A short delivery window was tightened further by a material delay, leaving multiple work fronts to be coordinated without diluting the installation standard.

The response

Two teams worked across the substations, sequencing the straight joints, LV and HV terminations, earth nests, internal earth tape, grating and testing.

Delivered scope

What TMRF completed.

Outcome

Both substation fit-outs were completed within the available programme despite the material delay and hot working conditions.