The challenge
The 300 mm² cables made the LV pillar installation physically demanding and required careful cable handling and positioning.
TMRFJointing
Discuss a project
Substation and LV pillar
Congleton
A multi-substation package combining large LV cable terminations with HV Euromold work and complete fit-out activity.

Three substation fit-outs
300 mm² cables
HV Euromold terminations
The workfront
The 300 mm² cables made the LV pillar installation physically demanding and required careful cable handling and positioning.
The team used the correct handling and termination methods to complete the LV pillar work neatly while progressing the associated HV and substation scope.
Delivered scope
Outcome
The combined LV, HV and fit-out scope was completed as one coordinated installation package.