The challenge
Access around both the transformer and the field-end terminations was limited, so the work sequence and tooling had to be planned around the available working space.
TMRFJointing
Discuss a project
33 kV terminations
Rotherham
A demanding 33 kV termination package across transformer, field and auxiliary equipment, completed around restricted access at both ends of the circuit.

630 mm² 33 kV cable
Transformer and field ends
Auxiliary transformer included
The workfront
Access around both the transformer and the field-end terminations was limited, so the work sequence and tooling had to be planned around the available working space.
The team prepared each termination position, controlled the cable arrangement and used the appropriate tooling to complete the main and piggy-back termination scope.
Delivered scope
Outcome
The complete termination package was delivered across the transformer, field and auxiliary equipment despite the restricted access conditions.
Have a similar requirement?