The challenge
A short delivery window was tightened further by a material delay, leaving multiple work fronts to be coordinated without diluting the installation standard.
TMRFJointing
Discuss a project
Complete substation works
Chesterfield
Two full substation fit-outs delivered as a tightly coordinated electrical package covering LV, HV, earthing, grating and testing.

Two complete fit-outs
LV, HV and earthing
Testing included
The workfront
A short delivery window was tightened further by a material delay, leaving multiple work fronts to be coordinated without diluting the installation standard.
Two teams worked across the substations, sequencing the straight joints, LV and HV terminations, earth nests, internal earth tape, grating and testing.
Delivered scope
Outcome
Both substation fit-outs were completed within the available programme despite the material delay and hot working conditions.